Risk · Interconnection Timelines

Grid & Interconnection

How long it takes to get a new electrical grid connection, by grid operator, for a large load (e.g. a data center) or a generator (power plant).

Confidence A Directly reported figure B Estimated / Derived C Regional inference / indirect estimate D Not found / insufficient data

Load wait and generator wait are separate queues — don't average them. Fast-track pathways (e.g. SPP's HILL) are excluded from headline ranges; see Status.

US markets (7)

7 MARKETS
Grid OperatorLoad Wait (yrs)Generator Wait (yrs)StatusDetailsConfidence
ISO-NE (US)7–101.05UnderwayTransitioning to first-ready-first-served cluster studies (FERC Orders 2023/2023-A); most tariff changes in effect, implementation ongoing.B
NYISO (US)5–76UnderwayTwo-phase generation cluster-study process live since Aug 2024; large-load reforms in development, FERC filing targeted Dec 2026.B
CAISO (US)5–5.69.2Partly completedCore reforms (FERC-approved) effective Oct 2024; Interconnection Process Enhancements 5.0 still in tariff development.B
PJM (US)3–41.5UnderwayTransition Cycle 1 complete; Transition Cycle 2 processing through end of 2026.B
MISO (US)1.5–33.5UnderwayQueue-improvement initiative active: queue caps, study automation, ERAS expedited studies; dedicated large-load expedited process in development.B
ERCOT (US)1–21.67CompletedPUCT-approved Batch Zero framework effective Jul 2026; batch studies replace project-by-project process for loads ≥75 MW.B
SPP (US)4.5Completed & underwayConsolidated Planning Process effective Mar 2026; HILL large-load fast-track approved, effective Jan 2026.B

International markets (9)

9 MARKETS
Grid OperatorLoad Wait (yrs)Generator Wait (yrs)StatusDetailsConfidence
TenneT (Netherlands)7–101.25Underway (Germany)Germany: criteria-based procedures replacing first-come-first-served for battery/large-consumer connections (Feb 2026). Netherlands: participating in faster grid-expansion programs.B
NESO / National Grid ESO (UK)8–1012.5Underway, stage 1 doneTMO4+ reform approved Apr 2025; new connections pipeline reordered. Gate 2 offer rollout continues through 2026–27.B
RTE (France)3–7UnderwayNew rules favor mature projects; consultation launched on consumption-customer reform. Not yet fully completed.B
TenneT (Germany)up to 70.25Underway / implementedMaturity-based process replacing first-come-first-served for large consumers and battery storage, as of Aug 2026.B
Amprion (Germany)up to 7UnderwayMaturity-based process for storage/large-consumer/data-center requests starts Apr 2026; completion not reported.B
50Hertz (Germany)3.5–6.53.5ImplementedMaturity-based procedure replaced first-come-first-served for large consumers/storage, effective Apr 2026.A
EirGrid (Ireland)0.625–1.51.5Underway, partly implementedDCCOPP v3 for data-center connections; generation/storage under new ECP-GSS batch framework.B
AEMO (Australia)2UnderwayAEMC rule-change process for large inverter-based load connection requirements; interim guidelines in development.B
DEWA (Dubai, UAE)None reported"First approved, first connected" queue; application bundling streamlined but not identified as queue reform.D