Britain's spare grid capacity

Where a new data center could connect to the grid today. 3,584 substations ranked by deliverable capacity, alongside grid supply point limits, transmission connections, retiring plant and 602 existing data centers. Select a substation to see its grid, market, planning, cooling and connectivity position.

Deliverable capacity
30.5 GW
After grid supply point limits. A further 8.9 GW of local headroom cannot pass through
Substations
3,584
Across 13 licence areas
Median deliverable
4.7 MW
66 sites exceed 50 MW and 11 exceed 100 MW
Data centers
602
393 operational · 183 planned · 26 under construction. UK Power Networks area: 1,184 MVA operational, 7,386 MVA pipeline
Data center load factor
23%
Mean of 5.4m half-hourly readings. Sites contract about 4× what they draw

Where the power is, and where the market is

Bars: effective headroom · dots: data centers · Network utilisation →

Capacity and market demand rarely sit in the same place. The East of England and South Scotland hold the most headroom, about 4.1 GW each, but the East has 117 data centers in its pipeline against 26 in South Scotland. South Wales has the least headroom, 1.2 GW, with 23 projects queued against it.

How much of a connection is used

Load profiles →

Sites contract roughly four times what they draw.

Show Min deliverable 0 MW

Everything else is in the search box on the map: networks (ukpn, ssen), levels (primary), sizes (1-5MW), layers (outages, power stations) and filters (greenbelt, water). Click the box for suggestions. Power & connectivity analysis →

National headroom map

1.0× · scroll to zoom, drag to pan
Legend
Deliverable capacity dot size grows with free MW Overlays transmission connection
GSP limit 400 MW+
200–400 MW
60–200 MW
under 60 MW
limit not published
agreement ending
internet exchange Data centers operational
planned
under construction
cancelled

Ranked substations

Available = what could be connected today · select a row for the full picture
Substation Network Level Available Connectability Contested Status

Detail

Hover or select

Candidate sites

Brownfield land councils have identified as suitable for development, ranked against deliverable capacity. Bands connect differently: a small site takes a supply from one substation, a large one depends on what the grid supply point behind it can deliver.

Size band
#SiteAcresNearest substationDeliverableWithin 5 kmTo exchangeOwnershipSignals
Methodology: how the numbers are derived Show · Elland worked example

Power reaches a site through a chain of equipment, each with its own limit. Published headroom is only one of them.

TRANSMISSION DISTRIBUTION National grid 400 / 275 kV Grid supply point the handover Bulk supply pt 132 / 33 kV Primary s/stn transformers your site Technical import limit what the system will permit 398 − 147 already flowing = 251 MW Local headroom what the transformers can carry published, less accepted offers = 273 MW Deliverable = the lower of the two 251 MW
Elland’s transformers could carry 273 MW, but the grid supply point above passes only 251 MW. Across the dataset this cap removes 8,900 MW at 458 sites.
Step 1 · Free now

Published demand headroom less offers the network has already accepted. Published, not estimated.

273.3 − 0.0 = 273.3 MW
Step 2 · Contested

Capacity offered to others but not yet accepted. Uncommitted, but someone else asked first.

400.0 MW · 1 applicant
Step 3 · Floor

If every outstanding application converts. With one applicant this is the outcome to plan against.

273.3 − 400.0 = −126.7 MW
Step 4 · Deliverable

The lower of Free now and the grid supply point’s own headroom. This is the headline.

min(273.3, 251.4) = 251.4 MW
Offer conversion by network (α)
What each network publishes

Published headroom is an estimate

No network measures spare capacity directly. Each one derives it from firm capacity less demand, using its own assumptions, so figures are comparable in direction rather than to the megawatt. Two differences matter when reading this page. Accepted and offered capacity is diversified at Northern Powergrid: it is scaled by connection type, about 0.8 for industrial, because no customer draws its full agreed capacity, so 400 MVA in the queue may appear as roughly 190. The other networks publish the raw figures. Grid supply point capacities are estimated: those assets belong to the transmission owner, not the distribution network, so the networks approximate them. Reinforcement dates are the transmission owner’s, and how much capacity a reinforcement releases is not published. Confirmed with Northern Powergrid, 17 September 2026.

Why an average is not applied to a single application

Roughly three in ten megawatts offered are accepted: 0.273 at UK Power Networks, 0.299 at Northern Powergrid and 0.340 at SP Energy Networks. The rate holds across a portfolio but says little about a single decision. 460 sites have one outstanding application and 443 have two or three. Those sites report the floor or a range, because a single application either converts or does not.

Requested capacity is not used capacity

UK Power Networks publishes 5.4 million half-hourly readings from about 100 operating data centers. Mean load factor is 13–29% of agreed capacity: 23.7% for colocation at HV, 28.9% for enterprise and 13.2% for colocation at EHV. Sites contract roughly four times what they draw. That inflates the queue, adds capacity charges and makes non-firm connections more viable than the headline megawatts suggest.

Grid import only

Every figure here describes capacity imported from the public distribution network. That is one route to powering a facility. A site with little or no grid headroom may still be viable through:

  • On-site generation: solar, wind, gas or fuel cells behind the meter, reducing or removing the import requirement.
  • Private wire: a direct connection to a nearby generator, bypassing the public network. The transmission connections layer shows where large existing generation sits.
  • Storage: batteries to shave peak import, letting a facility run above its firm connection for short periods.
  • Flexible or non-firm connections: accepting curtailment at times of system stress in exchange for an earlier and larger connection than a firm offer would allow.

Scale matters as much as route. Only 11 sites can deliver 100 MW+ from the grid; 970 can deliver 1–5 MW. The median of 4.7 MW is thin for a campus and ample for a distributed build, so use the scale filter rather than reading one headline figure as a verdict.

Connectivity

Straight-line distance from each substation to the nearest PeeringDB exchange facility with 10 or more member networks, and to the nearest major exchange with 100 or more (LINX LON1, LINX LON2, LONAP, LINX Manchester). It is not route distance and says nothing about fibre at the site. Sites more than 100 km from a major exchange get a carrier diversity check in their next steps.

Capacity counted once

SP Energy Networks publishes one headroom figure for a group of substations and repeats it on each substation in the group. Totals, medians and counts on this page count each group once (3,584 of 3,979 listed substations). The map still shows every listed location.

Definitions

Available is published demand headroom, less accepted offers, capped by the grid supply point above it. Contested is capacity offered to others but not yet accepted.

Coverage and limits

Covers UK Power Networks, Northern Powergrid, SP Energy Networks, NGED and SSEN Distribution across 13 licence areas. Electricity North West is not included: it restricts its capacity heatmaps. SSEN publishes headroom in MVA, which is shown here as MW, and a site that shares capacity with another network shows as 0 where SSEN gives no figure. SSEN sites carry no flood, green belt or water screening yet. Flood zones and green belt cover England only. Every figure is a snapshot of what a network can accept, not a connection offer, and takes no account of the works or cost of connecting. Capacity only shows as contested once an offer has been made, so a site already under discussion can look clear. Verify before relying on any figure.